Orangery Extension in Chalfont St. Peter

Orangery kitchen extension - Orangery Extension in Chalfont St. Peter

The clients wanted to extend the kitchen by opening it up into a large orangery, with utility room on the side.

The kitchen window is the one with the hose reel beneath it.

 

 

 

 

orangery kitchen

The CAD image.

 

 

 

 

 

Orangery kitchen extension - 2

The existing slabs were lifted as the mechanical excavator prepared to dig the new trenches

 

 

 

 

 

Orangery kitchen extension - 3

Loose earth and a drainage pipe mean shuttering was required

 

 

 

 

 

Orangery kitchen extension - 4

Further shuttering

 

 

 

 

 

Orangery kitchen extension - 5

Foundations ready to pour concrete

 

 

 

 

 

Orangery kitchen extension - 6

Concrete poured and a new soakaway dug, this is a big hole beneath the plywood board. You can see the pipe running from this back to the extension which will be connected to the rainwater pipes at a later stage.

We also dug out in preparation for a new patio to be laid at a later stage, once all the messy jobs such as plastering are complete. Using the dumper we bought in many tonnes of  granite chippings (Type 1 M.O.T.) for use as a base for the patio.

Top soil has also been saved for the client to use.

 

 

 

 

 

 

Orangery kitchen extension - 7

Brickwork being set out.  We use concrete blocks where there will be no visible brickwork.

 

 

 

 

 

\

Orangery kitchen extension - 9

The new base is being compacted.

 

 

 

 

Orangery kitchen extension - 8

Compaction complete.

 

 

 

 

 

 

Orangery kitchen extension - 10

Facing brickwork going up.

 

 

 

 

Orangery kitchen extension - 11

A local multi brick is a perfect match

 

 

 

 

 

 

Orangery kitchen extension - 12

Looking for a cup of tea?

 

 

 

 

 

Orangery kitchen extension - 13

The scaffolding will enable us to do a quicker, better and safer job of the brickwork and roof

 

 

 

 

 

Orangery kitchen extension - 15

Laser-levels are used to establish a datum around the site, but used correctly a line of string can be effective.

 

 

 

 

 

 

 

Orangery kitchen extension - 14

Walls almost to “plate height”

 

 

 

 

 

 

 

 

Orangery kitchen extension - 16

Ready for the roof

 

 

 

 

 

Orangery kitchen extension - 17

Roof structural underway and the start of the critical stage of removing some of the existing roof tiles

 

 

 

 

 

 

Orangery kitchen extension - 18

The large glulam beams form the structural opening for the lantern.

The deck is laid to slight falls, but the Sarnafil roofing can be laid flat.

 

 

 

 

 

Orangery kitchen extension - 19

The existing kitchen roof is temporarily sheeted over

 

 

 

 

 

 

 

Orangery kitchen extension - 20

A cold, dry day.

 

 

 

 

 

 

 

Orangery kitchen extension - 21

The kitchen roof needs to be opened up so we can weather the new roof

 

 

 

 

 

 

Orangery kitchen extension - 22

Sarnafil roofing laid

 

 

 

 

 

 

Orangery kitchen extension - 23

Eavesbeam of new hardwood lantern roof fitted.

 

 

 

 

 

 

 

Orangery kitchen extension - 24

Creasing tiles being laid

 

 

 

 

 

 

Orangery kitchen extension - 26

The boiler needs to be removed from the existing kitchen wall before we can fully enclose the extension,

 

 

 

 

 

 

Orangery kitchen extension - 27

New boiler fitted in utility area.

 

 

 

 

 

Orangery kitchen extension - 25

Lantern erected and glazed.

 

 

 

 

 

 

 

 

Orangery kitchen extension - 28

Ready to start the knock-through

 

 

 

 

 

 

 

Orangery kitchen extension - 29

knock-though in progress.

 

 

 

 

 

 

 

 

 

Orangery kitchen extension - 30

Kitchen door blocked-up, how to get to the wine!

 

 

 

 

 

 

 

Orangery kitchen extension - 31

Ceiling plaster-boarded.

 

 

 

 

 

Orangery kitchen extension - 32

Ceiling skimmed

 

 

 

 

Orangery kitchen extension - 33

Normally the walls are plastered before the floor is screeded, but better to screed the floor first in this case.

Aprrox 100mm of Celotex GA4100 insulation is laid, then underfloor heating pipes on top.

 

 

 

 

 

 

Orangery kitchen extension - 34

Screed laid. Again, this is done with a laser level and is perfectly flat.

The screed can start drying whilst other works are being done.

 

 

 

 

 

 

Orangery kitchen extension - 36

Walls plastered and painted. The screed is drying out well.

 

 

 

 

 

 

 

Orangery kitchen extension - 37

New kitchen delivered.

 

 

 

 

 

 

OLYMPUS DIGITAL CAMERA

The final result.

 

 

 

 

 

 

OLYMPUS DIGITAL CAMERA

Tiles to match the existing were sourced and extended out past the peninsula. New wood-effect tiles were laid in the lounge area.

 

 

 

 

 

 

 

OLYMPUS DIGITAL CAMERA

The ideal spot to enjoy the garden.

 

 

 

 

 

 

 

Orangery kitchen extension - 35

Final patio laid.