The hardwood windows, bi-fold doors and lantern have been installed, the next step is to fit the glass.
As we have a tight deadline to meet, we are also preparing the floor at the same time. We are laying 100mm Kingspan insulation on top of the concrete floor slab, the screed will be laid. Normally we would plaster the walls before laying the screed, however the screed will need time to dry out before the hardwood flooring is laid, therefore we need to get the screed down as early as possible. This will happen as soon as the roof glass goes in.
There will be electric underfloor heating laid within the screed. Ideally a warm-water underfloor heating system would be used, but it will not be possible to connect this to the existing boiler within a lot of internal disruption, something the clients wisely decided against as they have a stunning kitchen which has been recently decorated.